BIM and Digital Tools for State-of-the-Art Construction Cost Management

Samad M. E. Sepasgozar

Aaron M. Costin

Aaron M. Costin

Reyhaneh Karimi

Reyhaneh Karimi

Sara Shirowzhan

Sara Shirowzhan

Ezatollah Abbasian

Ezatollah Abbasian

Jinyun Li

School of Built Environment, University of New South Wales, Sydney 2052, Australia College of Design, Construction, and Planning, University of Florida, Gainesville, FL 32611, USA Department of Art and Architecture, University of Science and Culture, Tehran 1461968151, Iran

Department of Public Administration, Faculty of Management, University of Tehran, Tehran 1461968151, Iran

Author to whom correspondence should be addressed. Buildings 2022, 12(4), 396; https://doi.org/10.3390/buildings12040396

Submission received: 31 December 2021 / Revised: 10 February 2022 / Accepted: 21 March 2022 / Published: 24 March 2022

Abstract

Cost overrun has remained a key risk of construction projects that can be prevented by utilizing new technologies. This paper aims to identify the gap in the literature, which can potentially be addressed by using digital tools and technologies, by reviewing the current and state of the art practices. The paper presents the results of a systematic and critical content reviews on cost overruns, to address the question of what factors are affecting the cost overrun. This paper also reviews how building information modeling (BIM) in conjunction with other tools, such as the common tools in the Asia and Asia Pacific regions, are used for cost estimation and monitoring. The paper presents the results of the content review, including their contributions and limitations, which are also used to set key directions for future investigations. A total of 176 papers was identified to develop the construction cost management (CCM) dataset. The method was a mix of systematic reviews, including co-authorship network analyses, co-occurrence analytical map development covering 5671 keywords, and content analysis including theme identification and a critical review of selected papers. The paper critically reviewed 63 selected papers from CCM, which are divided into four clusters based on their scopes: BIM adoption for cost estimation and quantity surveying; BIM implementation for a bill of quantity, risk paths, and cost overruns; cost control and management; and, finally, BIM, virtual design, and value management. A trend analysis using a set of 16 themes (e.g., 3D model, BIM, Decision, Energy, and Life Cycle) for all the papers over the past ten years was developed. The content of each cluster of papers was reviewed based on the frequency of the selected themes in each cluster. The content of each cluster of papers was also reviewed critically and gaps were identified, so a set of directions for future investigations are presented.

1. Introduction

Cost overrun is one of the most impactful risks in construction projects, and, being such a dynamic and complicated factor, it has been difficult to fully mitigate. While there are many investigations on factors affecting the project cost variations, cost overrun remains the key concern of many projects and companies in construction [1]. The main reason is that the construction industry is very resource-intensive, so many projects face resource scarcity, cost variations of materials and equipment, unexpected costs, and incidents during the construction process [2]. Cost overrun refers to any unpredicted changes in a construction project budget that may affect the project’s total cost. Table 1 shows examples and evidence on cost overrun in different contexts and years. For example, Pilger, Machado [3] suggest that road infrastructure projects are complicated and require a diverse range of materials. Due to enormous variance in construction circumstances that might occur in different sites, road construction varies from other building and manufacturing processes. The nature of construction may affect cost overruns, requiring digital tools to monitor, predict, or control the project costs.

In the conventional project delivery, design documents are used to estimate the project cost before value engineering may be conducted for the final decisions about the design and alternatives. This process is repeated for alternatives and can be a time-consuming practice. Using new information systems and models such as 5D BIM, all the design options, including the associated costs of each design scenario, can be evaluated concurrently. However, more practice and lessons on how digital tools can efficiently be utilized are needed to enhance the process of cost estimation, which can be helpful in the financial management process. This study aims to review the current literature and identify the relevant gaps.

This paper aims to identify research gaps and develop future cost overrun directions based on a systematic search, and the selected papers are critically reviewed. This paper’s objective is to discuss new potential solutions to the problem of cost overrun, which still remains a common critical issue in construction projects. The initial step in this work is to identify articles in a methodical manner, investigating cost and cost overrun in construction. Next, a content analysis is conducted to thoroughly evaluate the relevant articles and offer a thorough grasp of the current literature. Finally, the paper analyzes the gap and develops directions for future investigations.

2. Review Method

The review method is designed based on two key research questions: (1) what factors are affecting the cost overruns? and, (2) what are the new technologies, techniques, and trends that can improve cost management or prevent cost overruns? To address these research questions, a systematic review is carried out to find relevant papers and reports. This article’s literature collecting and filtering technique is a wide, top-down strategy that gathers articles using broad phrases and queries first, then filters out those that may not be relevant to the research. This strategy, which comprises the three-step procedure below, has been proven to be more efficient than a constrained, bottom-up approach: (1) find and filter relevant publications; (2) classify and analyze articles for in-depth study; and (3) assess and synthesize the literature.

Various academic databases, such as Scopus and Google Scholar, are used for conducting a systematic search on the chosen topic. In addition, to ensure that relevant articles that may not have been included in a database would be identified, the references of selected articles were skimmed to find some more relevant papers to be considered in the present review.

Using a different set of keywords, articles related to cost control or management that may affect the project’s total cost were searched for and reviewed, generating the most common keywords to set the final search strings for a systematic review to make sure no key articles are missed. For example, one search string that was input was “cost overrun,” which resulted in over 1800 results. Since this included many irrelevant articles, more complex strings were used, such as ‘cost’ OR ‘cost overrun’, AND ‘construction industry’ OR ‘construction project’. Furthermore, to include different spelling and grammar (e.g., visualization, visualization, and modeling), we utilized the asterisk (*) function, which enables any characters following it (see Table 2). The initial search resulted in 176 papers. Applying the filtering criteria, including scope, years from 2010 to 2020 covering the recent decade of investigation in this field, journal articles in English, and duplicates that occurred in multiple queries, resulted in 104 records that will be used in the analysis.

Figure 1 shows the number of publications focusing on cost management from 2010 to 2021. Figure 2 also show the results of the search within Scopus, including 104 articles from different countries. Surprisingly, the selected search combination (refers to Table 2) shows that journal publications are limited to prior to 2010. However, the number of articles in the field has been increasing in recent years.

3. Bibliography Analysis

A bibliography analysis has been conducted, including co-authorship and co-citations, for determining the linkages between the construction cost management literature, based on the selected strings (refer to Table 2). The bibliography analysis, the analysis eliminates bias during the search, article selection and analysis. Based on citation records and cited references, the used bibliometric approach aids in discovering commonalities and likely patterns of research [39,40,41]. This helps scholars to learn from the current practice, including limitations and gaps, so that they can be filled in the future.

Figure 3 displays the outcome of a thorough counting method co-authorship analysis. An author’s minimal number of papers is taken into account as 2, so 2009 authors and co-authors of 337 selected research items were included and visualized in Figure 3.

The overall strength of co-authorship linkages with all authors and co-authors was determined for each of the 2009 researchers, and the strongest link strength was used to visualize Figure 2 and Figure 3. The co-occurrence analysis map of keywords based on the initial CCM bibliographic dataset is shown in Figure 4. Figure 4 shows a total of 1151 keywords out of a total of 5671 keywords for this visualization, with a minimum number of 2 for co-occurrence visualization.

The co-occurrence analysis map of keywords based on the initial CCM bibliographic data set is likewise shown in Figure 5, but the minimum number of co-occurrences was chosen as 2 to identify the most common themes. Figure 5 shows a total of 1151 from 5671 sample keywords.

Figure 6 shows that cost and cost-effectiveness are related to most of the high-frequency themes or keywords such as automation, BIM, construction projects, and buildings. The figure also shows that most of the keywords are repeated from 2016 onwards, which shows there might be a change in trending keywords and themes from 2010 to 2016; thus, further investigation is required. Figure 7 illustrates a co-occurrence network of keywords developed based on CCM.

4. CCM Content Review and Systematic Analysis

This section examines the content of the CCM data set critically, focusing on the subjects, keywords, and themes. First, the entire CCM data set were grouped into four main clusters, with each cluster against a few themes such as 3D model, BIM, cost-effectiveness, design, estimator, measuring, quantity surveying, and scheduling. The CCM data set can also be classified and analyzed based on their findings. Figure 8 shows that the CCM data set’s selected publications may contain at least four different types of conclusions, based on further content analysis: (i) the first cluster of papers focuses on BIM and 3D modeling for cost estimation and quantity surveying, including 22 papers; (ii) BIM implementation for developing a bill of quantity, risk paths, and cost overruns, including 13 papers; (iii) cost control and management, including 6 papers; and (iv) the fourth group investigates BIM, virtual design, and value management, including 20 papers.

Figure 8 and Figure 9 show that some themes have received much more attention in recent years. For example, BIM and 3D models might be the core part of figures. In cost management papers of the CCM data set, energy and life cycle have received very little attention before 2015, but they have gradually been discussed in recent years. These themes are suggested to be investigated more in cost management literature. Particularly, these themes can be coupled with emerging technologies such as Blockchain, and case studies using these technologies can be useful for practitioners [42].

In this study, the reviewed papers are divided into four groups based on their scope: The first set of papers worked on BIM adoption for cost estimation and quantity surveying, such as [43]. The second set investigated BIM implementation for a bill of quantity, risk paths, and cost overruns, the application of new cost estimation methods such as simulation techniques or the application of BIM in construction projects; refs. [9,44] are examples, respectively. The third set includes papers on cost control and management not as the main objective but as a par. For instance, ref. [45] tended to provide a teaching method for a web-based BIM and cost-estimating system, ref. [46] aimed at comparing the cost of buildings built with conventional and industrialized construction methods, while partly explained the cost estimation methods for two mentioned buildings, and ref. [47] found out that cost estimation can be improved by using BIM. In addition, the fourth set included papers investigating BIM, virtual design, value management, and causes of cost overrun, such as [48].

Lawrence, Pottinger [43] focus on a case study of concrete footings take-off computation using Revit and on-screen take-off. They offer a new BIM-based estimating app named Innovaya, which recognizes design information with various formats created in Revit, AutoCAD, or Tekla. The data (e.g., dimensions of walls) are associated with dimensions of the assembly. So, Innovaya recalls this mapping, and, in case the design is revised, the assembly quantities are recalculated or updated in a semi-automatic process, in which every managed quantity matches to a component and can be exported to a spreadsheet or joined with a chosen commercial cost database in order to do the quantity calculation. Lawrence, Pottinger [43] propose cost estimate method, which has the following functions: create views that are automatically made by BIM utilizing inquiry evaluation software; create estimate based on the input data using the Master Format standard; update BIM while the design is in process, which is considered as a reference for comparing the views; and update the estimations when the estimators get a group of estimate changes, by which they can be informed about every change and make a decision about the way the estimate must be updated. However, the efficiency and effectiveness of the method are only evaluated by 14 students with a computer science background. This method needs further assessment and validations using a larger sample of quantity surveyors, and the outcome should be cross-validated by different case studies. This type of method is critical, since the current estimation methods need to be shortened in terms of updating the estimate when either the design has changed or there are many change orders.

Wu, Wen [45] propose a web-based BIM and estimating tools for training purposes. Thus, students are able to estimate the cost in a different way. To evaluate the model, a construction case project was given to each group of students for practicing BIM and cost estimation. The system is described as follows: (1) a 3D BIM model should be built, (2) the info of the model should be developed, (3) the equipment characteristics of the model should be configured, (4) each component quantity of the model should be developed, (5) in order to integrate data and transfer to a web-based system, (6) unit price analysis should be completed as well as the cost of each component should be estimated, and (7) the total cost required to be estimated. In order to evaluate the model, 42 students and 32 experts were participated in the survey, which is designed based on TAM3. The results of this survey are then compared to the professionals’ and beginners’ intentions to use the proposed system by this study. The professionals have three years or more of industrial working experience and are able to estimate costs and produce design drawings of construction projects. The beginners are senior university students in the field of architectural design in Taiwan, who recently received certificates in quantity estimation and design. The variables that are studied are job relevancy, result demonstrability, self-efficacy, usefulness, and user intention to accept the system. Summaries of articles are included in Table 3, Table 4, Table 5 and Table 6.

The research by Lawrence, Pottinger [43] aims at creating and maintaining a cost estimate taking advantage of flexible operation that associates each element of BIM with elements of cost estimation. Performance 1 (CP1) and CP2 are obtained as two detailed cost estimates (due to the changes in design, CP2 is prepared 16 weeks after CP1) and cost analysis features such as code, unit of measure, unit rates, and total quantity. The article explains a process of concrete footings as an example of a detailed take-off, by which reaches a conclusion that: the aggregating process of the mentioned various quantities for every cost item needs a large amount of time and effort. The interviews revealed that when changes in design happen, each revision leads to a big deal of manual work to review the new drawings with new changes, which also to update the On-Screen Take-off quantities. Based on both the mentioned weak points and how BIM-based estimating apps are able to address many drawbacks of the methods depending on 2D paper or digital drawings, the research then evaluates a new BIM-based estimating app named Innovaya, which is explained more in the table. The paper concluded Innovaya is useful for take-offs because the model relies on how categories are organized in the BIM. In particular, the cost items that are used by the cost estimator should be matched to the category of building components in the BIM. Specific mapping types are emphasized in order to coordinate and update the cost estimate: (1) proxies, (2) aggregated conditions, and (3) spatial conditions. Proxies, which are mapping features, can be useful for cost estimators in order to connect a design to a cost estimate so that the estimator can utilize relevant building elements as proxies in the early stages of a project when exact specifics are lacking. Aggregated conditions are responsible for characterizing categories of building elements beyond BIM components to change a component whenever items of another component group are changed. The spatial conditions and geometric configurations of building components significantly affect the cost and design constructability. Moreover, the greater number of changes that happen in an item feature results in less repetitive work, ultimately decreasing productivity. Therefore, the estimator should be informed of any special configuration change in every revision. The proposed cost estimate method by this study is as follows: (1) Making project mappings by a data modeler who is a professional cost estimator, plus a professional person familiar with BIM to formulate inquiries. (2) Creating views, which are values for mappings, automatically made by BIM utilizing inquiry evaluation software based on the mapping definitions. (3) Making an estimate, when the cost estimator makes the project estimate. The input data is formed based on the Master Format standard. The views made in the previous stage play the role of a controller for the estimator in making the cost estimate. (4) Updating BIM while the design is in the process by the party (or the Architect), which is considered as a reference for comparisons. (5) Comparing the views, in which a new group of views is created by evaluating the inquiries in the mappings. Moreover, (6) updating the estimate, when the estimators get a group of estimate changes, by which they can be informed about every change and make a decision about the way the estimate must be updated. Sometimes, without estimators’ intervention, the estimate can be updated in an automatic manner, although without the estimators’ control, this kind of automation may lead to incorrect action. Therefore, the proposed system informs the estimator about the change and provides the estimator important data to accept the suggested changes or make more refinements if necessary. Thus, this process can sometimes be called semi-automatic.

Wang, Wang [49] propose a BIM model for cost estimation. The Public Construction Cost Estimation System (PCCES) is adopted because it is a common system in Taiwan. In future works, the modelling processes should be conducted frequently to update the progress curve as the project proceeds in order to add more automation to the suggested model, and this application needs to be examined. Faghirinejadfard, Mahdiyar [46] calculate and compare the cost of two similar buildings using the IBS and CBS methods. The following comes to the cost estimation methods utilized by this research for two buildings. In the CBS method, the 3D models are first imported into Navisworks Manage, while all building materials are defined in detail connected to Resource Catalog components. Next, the mentioned materials are allocated to the related groups. Lastly, quantity take-off is taken in an automatic way for all building parts that are created on the 3D model. The required construction activities for each part of the building are collected according to their preference and kind of relationships with previous and next activities. In addition, every activity unit price is taken from the Malaysian Public Work Department (JKR) price list, including resources such as machinery, labor, and materials. This research framework is as follows: (1) data collection, from Malaysian rules and market conditions, and the price list of the Malaysian Public Work Department (JKR); (2) modeling a case project located at Universiti Teknologi Malaysia that has different plans (on a plan for IBS and another for CBS methods) by means of Revit including foundation, beams, exterior and interior walls, columns, etc.; (3) exporting the 3D models to Navisworks Manage, calculating the construction cost of each building, doing quantity take-off; (4) estimating 5D and 4D according to the data from the previous step by presenting the project WBS made in the Navisworks Manage; (5) extracting different advantages of prefabrication method from the previous research that affect the process of onsite construction and contribute to a decline in some costs; and (6) using Microsoft Excel and the visual graph, analyzing the influence of time on a comparison of two building techniques according to the Break-Even Point (BEP) analysis, Return on Investment (ROI), and each project value. The findings show that there is a considerable difference between the CBS and IBS methods for construction cost (the total figure for the project built conventionally was $ 62,392, whereas that of the industrialized one was $ 88,012).

Abanda, Kamsu-Foguem [50] illustrate a graph of the process of cost estimate in a BIM cost estimating software. This research also reviews the literature about intelligent cost estimation methods and provides information about: (1) the previous works in terms of cost estimation to some extent, (2) BIM-based construction cost estimate, and (3) BIM-based cost estimate tools and measurement rules. The ontology is evaluated semantically by six participants. In order to check the ontology syntactically, the Manchester OWL syntax validator is used. Then, this study takes advantage of Navisworks for a building that is used for ontology validation. Since the proposed ontology is only validated in Navisworks, it is recommended to be tested on other tools such as Autodesk Quantity Take-offs (QTO). End-users can also adapt or modify the proposed ontology so as to meet their different requirements.

The paper by Babatunde, Perera [44] suggests that BIM applications should be developed for quantity surveying and cost estimating. They reviewed the literature, pilot studies, and a questionnaire survey of both BIM users and non-users who are practitioners in Nigeria. They conduct a survey using 73 participants, including 31 users and 42 non-users. However, this investigation was restricted to quantity surveying companies, so it suggested collecting the survey from the standpoints of clients and contractors with a comparison with other countries with similar conditions.

The study by Juszczyk, Zima [51] conducts a simulation and develops a large number of neural networks (called an ensemble). Taking advantage of a model with a number of networks instead of a model using one network is the main difference between this study’s approach and the traditional use of neural networks. According to neural network ensembles, this research develops four construction cost predictors (models) of sports fields. The model’s variables, nature, and their values are related to the characteristics of sports fields as special facilities and their construction costs. A set of individual multilayer perceptron neural networks forms the ensembles, two of which (ENS 1 and GEN 2) are created by the set of networks that differ in their architecture and activation functions, while the rest two ensembles (ENS 3 and GEN 4) are created with the networks of similar architecture and activation functions. In this investigation, the cost analysis process takes advantage of the BIM model availability in terms of fast data extraction and the necessary info as input for the proposed models. This study shows that: (1) all four proposed models perform well in cost prediction in the conceptual estimates. (2) they are superior to the models based on single neural networks due to the low MAPE errors computed after testing, which is between 2.73% and 3.91%; and (3) the results of the BIM-based cost estimation show the efficiencies of the models, as Absolute Percentage Error (APEs) errors are lower than 10%. A convergence in predictions is obtained, and error variation is small. The GEN 2 ensemble obtains the most efficient prediction of the case study. The predictions are created for the cost values updated for only a special year, which is the limitation of this work, and this matter is suggested to be investigated carefully in future research. Also, all predicted APEs for testing cases are smaller than 10%. This shows a satisfactory result and acceptable variation in the predictions from the real-life construction costs.

A study by Alrashed and Kantamaneni [62] develops and evaluates 5D BIM for housing projects to evaluate the perception of participants in the Kingdom of Saudi Arabia (KSA) housing types. Alrashed and Kantamaneni [62] adopted two-path analysis methodology: (1) Path One: survey analysis to learn participants’ opinions about the case house styles. (2) Path Two: create a 5D BIM as well as a construction costs estimation. In this paper, firstly, 3D CAD models of mid-terrace houses are made in ArchiCAD. Secondly, the created models are exported to Vico software. Thirdly, 3Ds are activated, and material codes are stored as a library that includes the unit rate of materials. Fourthly, they are transferred into Excel in order to calculate the precise model quantities automatically, in case any change in design or recalculation will be needed, so that the final bill of quantities (BOQ) of the mid-terrace houses of this study can be created. It is shown that: (1) The traditional methods of cost estimation use simple tools and software (such as Excel for calculating project unit prices and historical data), in comparison with new methods including various techniques such as the ones used in this research leading to a more accurate cost estimate. (2) The proposed 5D BIM declines the costs considerably by reducing material waste and time clashes.

The work by Ali, Mustaffa [53] proposes a framework to improve the Quantity Surveying (QS) knowledge and skills to answer the demand of industry for BIM graduates. The proposed framework is aimed to support the Malaysian industry and government initiatives to BIM implementation. It also encourages the utilization of BIM for higher education, and professional training. Developing the curriculum to increase the students’ and lecturers’ perception and extending it for higher graduate courses are recommended for future works.

A study by Lee, Kim [54] presents an ontological inference of work items that activates search (automated) of the most suitable work items and their connected unit costs. It includes semantic data for work items and conditions, also a semantic reasoning rule, which enables the ontology. A case study evaluation by this study showed that the proposed work could perform in real situations. The proposed approach used for building cost estimation can help engineers more easily use BIM info from IFC XML and can be useful in the automation of the entire estimation process.

Niknam and Karshenas [55] present a novel technique for quantification, which uses semantic web tools using a machine-processable data modeling that allows data sharing via online tools. The estimating method proposed in this work depends on BIM, knowledge of estimation, and the data of construction material in a web ontology language. An estimating app is presented in this work, which combines distributed information given various stakeholders to prepare cost estimates. This paper intended to simplify the process by decreasing people’s involvement in repetitive activities of cost estimating. The estimating app is examined in a comparison with the WinEst tool. The findings show that the approach can increase the estimators’ efficiency substantially. It shows that, although the estimating databases have many resources and material databases should be updated before each cost calculation, this method may substantially increase the estimating efficiency.

Amuda-Yusuf and Mohamed [56] investigate the need for creating a Building Service Standard Method of Measurement (BSSMM), which allows quantity surveyors to manage the cost of building operation and services. A questionnaire was designed and the outcome of the survey identified 23 items of the chosen standard; they were categorized into three groups and are ranked. Boktor, Hanna [57] conducted another survey and examined an application of BIM in the mechanical construction industry. It is based on an extensive survey and interview of 27 questions including: (1) organization background, (2) current BIM applications, and (3) BIM application in the future. The majority of the respondents (68%) are American, and the rest (32%) are Canadian. It is shown that: (1) 58% of mechanical contractors had experienced BIM for less than three years. (2) The implementation cost of BIM was reported as less than two percent of the total project cost. (3) Above 70% of participants confessed that BIM decreases conflicts and improves coordination of the project.

Wen [58] suggests that the construction projects should integrate BIM with the lean construction concept, both of which can play an important role in the cost control of the construction projects. The findings of a case project examination indicated that the integration of lean construction and BIM is able to control cost-efficiently, decrease the activities that are non-value-added, and eventually increase the project value and meet the clients’ requirements.

Marzouk and Hisham [59] propose BIM applications in bridge projects in terms of cost and time analysis and management. The cost estimation application is able to do with an approximate or detailed cost estimate. It is designed flexibly to be used with either default or defined values. Various acting measurement indexes are used to control the project cost and schedule over the implementation phase of construction. The application combines BIM and the concept of Earned Value (EV) in order to investigate the project state at special dates. A case study is then used to show the application of the presented modules. The findings indicate that, even though the presented cost estimation modules help the cost estimation of bridges, it is restricted to direct costs that are related to only materials, labor, and equipment. The module does not consider indirect costs such as overheads, taxes, bonds, insurances, and contingency.

Wu, Wood [60] investigate the cost calculation practices and methods in the UK, including the effect of the application of BIM. Several important problems have been identified related to information exchange, model quality, and UK standards. This paper reviews the current BIM tools of cost estimation in the UK context, so that the ability of the current BIM functions for supporting the UK quantity surveying can be examined. The four most famous reviewed tools in the UK are the Solibri model checker, Autodesk QTO, CostX, and Causeway BIM measure. The results of the review indicate that most of the tools cannot support the UK practice in an automatic manner, and more investigations are needed to use them in the UK projects. As an example, Solibri is capable of checking models, CostX is capable of visualizing the models, and CATO is able to be integrated into the BIM measure.

The study by Jrade and Jalaei [63] integrates building management systems, Life Cycle Assessment (LCA) tools, and a database of sustainable construction project designs. Integrating BIM (3D), an LCA, a certification, and a cost module was considered and aimed to make the sustainable designs easier. A real construction project is provided to show the effectiveness and abilities of the mentioned model. The proposed model is easy to use because it needs fewer user inputs and provides error prediction. Its benefits include decreased time, quicker calculations, and reliable output reports. However, it contains the following limitations: (1) the model cannot be used during construction; (2) the database was developed based on limited BIM files with limited components; and (3) the model does not work fully automatic.

Popov, Juocevicius [64] analyzes the use of BIM, computer-assisted tools, and simulation methods of building process according to the idea of Virtual Project Development. A cost estimation based on a Computer-Aided Evaluation System (CAES) in the BIM environment is summarized in the following figure by this paper. It is shown that the application of BIM on the 5D concept over the whole project lifecycle leads to some merits such as (1) supporting visualization and information; (2) simplifying the creation and sharing the data related to design, building, and keeping the buildings during their whole lifecycle; and (3) a computer-aided examination tool in construction, according to BIM, makes a link between structural design, cost estimation, and scheduling. According to Migilinskas and Ustinovichius [65] and Popov, Mikalauskas [66], the computer-aided evaluation system (CAES) can enhance the time efficiency of the project up to 40%, which may be required for design and the estimation.

Shen and Issa [61] develop a quantitative estimation for evaluating the effects of BIM-Assisted Detailed Estimating (BADE). In addition, it examines the effect of visualization factor and its compound effect and aggregated calculation factor on the building cost so as to understand the estimator’s cognitive details. Two BADE tools are examined to distinguish the influence of the visualization component on estimate from the combined effect of both the visualization and aggregation functions on estimation. A set of case studies with varying levels of estimate complexity are produced and tested using entry-level estimators using both traditional and BADE methodologies. The evaluation results show that the BIM-assisted estimation outperforms the conventional estimation methods. The visualization and aggregation performances of the BADE tool have a considerable effect on the function of the detailed estimate. The research depicts that the more complicated the estimation become, the fairer the benefits obtained from applying BADE tools instead of conventional estimation methods. It is also mentioned that, in order to get more conclusive results, more research on industry-level cases and subjects is needed. Table 7 includes summaries of papers related to digital modeling and cost management.

5. Project Cost from Project Management Methodology Perspectives

The Project Management Body of Knowledge (PMBOK) [67] defines cost management as estimating, budgeting, monitoring, and controlling costs. Moreover, it is about managing the daily costs of a project. This term is different from the term financial management, which refers to revenue resources for financing and its profit on investment, cash flow, and investment payback analysis.

Construction estimations can be categorized from simple estimates to complex ones, and it includes direct and indirect costs. The costs that are directly caused by specific scope of work and include costs of equipment are direct ones, while indirect costs may not be related to a special scope of a task and might be relevant to several scopes of the project.

The cost of the required resources is established in cost management, including operation costs and project life cycle costs. The plan needs to be customized to the requirements of the client, while also considering the other project stakeholders’ requirements. Cost management planning needs to be managed through the process of design to improve the possibility of estimating from the design phase and indicate the way the bill of materials (BOM) will be prepared.

To save time and cost, increase project performance and quality, and improve the performance of a design-to-cost facility, life cycle costing, value engineering, and constructability analysis are essential aspects used in the earliest planning processes on construction projects and enhance the decision-making process. Cost planning starts with estimating and the process of changing into budgeting. The terms bill of materials (BOM) and material take-offs (MTOs) refer to measure material quantity. Bill of quantities (BOQ) is another term referring to a database or spreadsheet that lists quantities of various items such as materials, equipment, and labor.

Estimation accuracy depends on the quality of the scope definition. The accuracy also increases as the project progresses within its life cycle.